Developing the archaeological village of Thi Ain
Developing the archaeological village of Thi Ain

Developing the archaeological village of Thi Ain

Project name: Developing the archaeological village of Thi Ain

Project No.: 19/14/501/58/00/00/4

Contractor Name: Saeed Murdad Al-Zahrani Contracting Est

Project cost: 1,900,000 riyals

Total project duration: 360 days

Completion rate: 20%

Elapsed time: --

Project Status: Paused

Site handover date: 12/29/1436 AH

The last action on the project: the return of costs was submitted to the Secretariat by letter No. 4400223652 on 03/17/1444 AH, and a request to add costs was submitted to the Ministry of Finance based on the letter of His Excellency the Undersecretary for Support Services No. 4400223652 on 03/24/1444 AH

Scheduled completion date: --

10 Dec 2022 - 03:15 PM

Similar news

Latest and important news
Arrow
Data Privacy

Al-Baha Municipality website uses cookies to identify the user and understand his needs as a user to provide ease of access and a better user experience. By continuing to use this site you agree to this site's privacy notice.

Privacy Policy
Last modified: 09:00 AM - 01/08/2026 Saudi time.

Was this page helpful?

0% From users said yes from 0 Comments

Was this page helpful?

Sort By

Your reply has been successfully sent

0% From users said yes from 0 Comments