Asphalting the grant schemes for the municipal garage scheme in Al-Makhwah Governorate
Project name: Asphalting the grant schemes for the municipal garage scheme in Al-Makhwah Governorate
Project number: 19/001/000/408510000/3111311
Contractor's name: Al-Masar Al-Arabi General Contracting Company
Project cost: 1,304,100 riyals
Total project duration: 180 days
Completion rate: 17%
Elapsed time: 50%
Project Status: Ongoing
The date of handing over the site: 19/1/1444 AH
The last action on the project: In progress
Scheduled end date: 7/19/1444 AH