Constructing gardens, corridors and squares - Constructing Al-Qafeel walkway
Project name: constructing gardens, corridors and squares - constructing Al-Qafeel walkway
Project number: 19/14/501/406059901
Contractor Name: Saeed Murdad Al-Zahrani Contracting Est
Project cost: 1,245,832 riyals
Total project duration: 517 days
Completion rate: 65%
Elapsed time: 86%
Project Status: Ongoing
The date of handing over the site: 1/21/1443 AH
The last action on the project: The project was resumed after the suspension on 3/27/1444 AH
Scheduled end date: 6/7/1444 AH