Project name: Preventing the dangers of floods for the Municipality and its affiliated municipalities
Project No.: 19/14/001/406020600/31131544
Contractor's name: Al-Mashi Platinum Contracting Est
Project cost: 4,913,700 riyals
Completion rate: 100%
Elapsed time: 100%
Project Status: Completed
Treatment of visual distortion, the second phase of Al-Makhwah Governorate, Al-Baha Region
Asphalting grant schemes, a second phase for the municipality of Al-Makhwah
Developing the archaeological village of Thi Ain
Asphalting of grant schemes, third phase for the municipality of Al-Makhwah
Asphalting, sidewalks and lighting for the Municipality and its affiliated municipalities
Treatment of visual distortion, the second phase of Al-Makhwah Governorate, Al-Baha Region
Asphalting grant schemes, a second phase for the municipality of Al-Makhwah
Developing the archaeological village of Thi Ain
Asphalting of grant schemes, third phase for the municipality of Al-Makhwah
Asphalting, sidewalks and lighting for the Municipality and its affiliated municipalities
Al-Baha Municipality website uses cookies to identify the user and understand his needs as a user to provide ease of access and a better user experience. By continuing to use this site you agree to this site's privacy notice. Privacy Policy